John Flanagan and Sean Dixon re-rendered chimneystack, replaced

lead work with new code 3 and code 5 lead respectively; all in full

compliance of Lead Code regulations.

Re-slating with reclaimed Welsh slate roof covering in Green Hammerton,

York.  Re-building chimneystack with lime mortar.  Replaced the

box gutter with new code 5 lead.  Replaced guttering with a new aluminium

OG profile system along with new cast aluminium rain water pipes.

Completed a re-roofing project in Weetwood, Leeds 16 with random

diminishing courses in Burlington slates, using  permeable breather able

under slaters felt.  Replacement lead valley with new code 5 lead.  Supplied

and fixed rigid board insulation in compliance with current Building

Code regulations.  Re-lined stone eaves guttering with lead together with

lead burnt outlets.